Development of project documentation (stage of RD) for performing search works (geodetic works) for the construction of "Overhead 220 kV SS 220 / 6-6 kV, expansion of the PPB-220 into two cells under the project" Construction of the complex for the processing of man-made waste TSKVZ (I-stage) , in particular, the design of a 220 kV overhead line (12 km) with a deflection of 1 km on the 220 kV substation "TsKVZ".